New build electrician in the Illawarra: a stage by stage checklist
A new home has 4 electrical stages: connection, rough-in, fit-off and final testing. The choices that cost most to change come early, before walls are lined. This checklist shows what to decide at each stage and what paperwork you should end up holding.
Start with the plans, not the walls. Decide power point and data positions, lighting, outdoor power and any EV charger or solar plans before the frame is lined. Engage an accredited service provider early for the connection, keep your builder's schedule in mind, and finish with a tested system and a Certificate of Compliance for Electrical Work.
What are the electrical stages of a new home?
Names vary between builders, but the order is nearly always the same.
| Stage | What happens |
|---|---|
| 1. Connection | An accredited provider arranges the supply from the network to the site |
| 2. Rough-in | Cables are run through the frame before walls are lined |
| 3. Fit-off | Power points, switches, lights and the board are fitted after lining |
| 4. Final test | Circuits are tested, the work is certified and supply is energised |
Your biggest say is at stage 2, because cable positions are fixed once the plaster goes up. That is the reason to talk to an electrician before the frame inspection, not after it.
What should you decide before rough-in?
Walk through the plan room by room, with furniture in mind. The usual gaps show up in the same places, so check these.
- Power points near where beds, desks, TVs and kitchen appliances will really sit.
- Data and network points for a home office. Our home office power and data guide goes through the options.
- Outdoor power and lighting for the garden, deck and driveway. See outdoor lighting planning.
- Kitchen circuits for an oven, cooktop, dishwasher and island power. The kitchen electrical planning page covers it.
- Space and cabling for a future EV charger or solar system.
- Switchboard size, with spare room for added circuits.
For the overall load, home electrical load planning explains how to add up what the house will draw.
Have plans and want them checked?
Send the electrical plan or floor plan with your suburb. We will mark the gaps before your frame inspection.
How does the power connection work on a new Illawarra home?
Endeavour Energy serves the Illawarra and the South Coast of NSW, and it publishes the steps for connecting a newly built home.
- Choose and engage an accredited service provider (ASP).
- Confirm the connection type. A new home needs a new connection, described as first-time power supply to a new home or structure.
- Your ASP usually submits the application through the Connections Portal.
- Respond to any requests for more information, and pay any fees.
- Receive the connection offer, which sets out costs, timing and next steps.
- Complete site works, which can include trenching, metering or a private pole.
- Endeavour connects the service once everything is ready.
Endeavour says costs vary with the service type, the site and extra work, and that your ASP can quote on your actual job. For what an ASP level means, read our Level 2 electrician guide.
Which estates and suburbs does this apply to?
The same stages apply anywhere in the region, from infill builds in older suburbs to new estates. Our Dapto page covers a suburb where newer estates are common, and the Illawarra area page lists the wider region. Your builder or estate may also set rules for items such as meter box position, so ask for the estate guidelines before you finalise the plan.
What paperwork should you hold at handover?
The person who tests the electrical work must submit a Certificate of Compliance for Electrical Work (CCEW) as soon as practical and no later than seven days after the test. From 1 July 2026 these go through the BCNSW eCert portal. NSW says you can give your email address so you receive the certificate automatically, or download a copy.
- The CCEW for the electrical work.
- The connection offer and approval from the network provider.
- Any warranty or product details for the board and fittings.
- A list of what each circuit supplies, so labels match the board.
New solar and batteries have their own commissioning path. NSW says that from November 2026 these systems, up to 200 kW, are commissioned through the NSW CER Installer Portal, which sends the certificate automatically. Our certificate and licence guide explains the CCEW in more detail.
What should you ask your builder about the electrical scope?
Building contracts often list electrical items in a general allowance, which can hide what is and is not included. Ask for the detail in writing before you sign off the plans.
- How many power points, lights and data points are included, and how much each extra one adds.
- Who arranges and pays for the network connection and any trenching.
- Where the meter box and switchboard will be fitted, and whether that can change.
- Whether smoke alarms, outdoor lighting and a charger-ready cable run are part of the base price.
- When the electrician will be on site, so you can inspect the rough-in before the walls close.
For smoke alarm rules that apply to homes, see our smoke alarm compliance page.
What happens when you enquire?
- You send your suburb, the plans if you have them and your builder's name.
- We tell you what to decide at each stage and which electrician type the job needs.
- You receive a written quote for the scope you choose. Prices are on the pricing page.
New build questions
When should I talk to an electrician about a new build?
Before the frame goes up, while the plans can still change. Decisions about power point positions, data points, outdoor lighting and a future EV charger are cheap to make on paper and expensive to fix once walls are lined.
Who applies for the power connection on a new home?
Endeavour Energy says you choose and engage an accredited service provider (ASP), who usually submits the application through its Connections Portal, though you can submit it yourself. Endeavour then issues a connection offer with costs and timing.
Will I get a certificate when the electrical work is finished?
Yes. The person who tests the electrical work must submit a Certificate of Compliance for Electrical Work, no later than seven days after the test. NSW says you can give an email address to receive it automatically.
Does my builder choose the electrician?
Often the builder's contract names the electrician, but many builders allow owners to ask about options or upgrades. Ask early in writing, and check the electrician's licence on the NSW Government licence check.
Can I add an EV charger or solar later?
Yes, but planning ahead makes it simpler. Increasing a home's power capacity, for example for an EV charger, can involve the network provider, so ask your electrician what to allow for at the board and in the cable runs.
Building in the Illawarra?
Tell us where the block is and what stage you are at. We will point you to the next decision.
Sources, checked 15 November 2026: Endeavour Energy, connecting a newly built home; NSW Government, Electrical compliance requirements; NSW Climate and Energy Action, altering supply.